S/2903/14/OL

22-Dec-2014

29-Dec-2017

Outline Planning (Large Major)

29-Dec-2017

Elsworth CP Cambourne CP Caxton CP

Land to the West of Cambourne (Excluding Swansley Wood Farm)

Development of up to 2,350 residential units including affordable housing; retail, use classes A1-A5 (up to 1.04 ha); offices/light industry, use class B1 (up to 6.25ha); community and leisure facilities, use class D1 and D2 (up to 0.92 ha); Two primary schools and one secondary school (up to 11 ha), use class D1; three vehicular access points including the extension and modification of Sheepfold Lane, a four arm roundabout provided on A1198/Caxton Bypass and an access point off the A1198, south of the Caxton Gibbet to serve the proposed employment uses; a network of segregated pedestrian and cycle routes; sustainable drainage system and other infrastructure; together with associated earth works, parking, open space, including equipped play, playing fields and landscaping.

Decision Issued

The individual or committee has signed off the recommendation by the planning officer, either approving or refusing the application. The applicant will then be notified by letter confirming the decision.

This application has already been decided. You cannot comment on it

Decision Details

Approved 

29-Dec-2017 


Publicity Details


27-Jan-2015 

17-Feb-2015 

Conditions/Reasons For Refusal

Type Short Desc
Condition Approved plans
Condition Site-wide Green Infrastructure and Biodiversity Management Plan
Condition Site-wide surface water drainage strategy
Condition Site-wide Sustainability Strategy
Condition Site-wide Employment Land Delivery Strategy
Condition Site-wide retail land delvery strategy
Condition Landscape details
Condition Tree protection
Condition Local areas of play
Condition Youth facilities and children’s play provision
Condition Allotments
Condition First reserved matters
Condition Biodiversity measures
Condition Lighting
Condition Walking and cycling provision
Condition Parking
Condition Highways adoption strategy
Condition Noise
Condition Extraction equipment
Condition Waste
Condition Affordable housing
Condition Market housing mix
Condition Last reserved matters
Condition Sustainable design and construction
Condition Cycle storage
Condition Detailed surface water proposals
Condition Site-wide Construction Environmental Management Plan (CEMP)
Condition Site-wide Construction Waste Management Plan (SWMP)
Condition Air quality
Condition Foul drainage
Condition Noise impact assessment
Condition Management of pillbox
Condition Detailed Construction Waste Management and Minimisation Plan
Condition Commencement of reserved matters
Condition Ground conditions and remediation works (EA)
Condition Construction Method Statement (CMS)
Condition Archaeology
Condition Playing fields
Condition Fire hydrants
Condition Access
Condition Planting
Condition Piling
Condition Playing fields
Condition Public art
Condition Approval of reserved matters
Condition Fibre optic
Condition Street lights
Condition Development quantums
Condition Phasing plan
Condition Design code
Condition Landscape management plan
Informative Noise
Informative Drainage
Informative Welfare
Informative Anglia Water
Informative Extraction equipment
 

HTS Name: wphappdetail02-default.hts
Logical ID: WPHAPPDETAIL
Stonewall, Gay and Lesbian Charity - opens in a new windowBeacon Authority logo